AltEn Facility Remediation Response
Updates from the AltEn Facility Response Group (FRG) on remediation efforts at AltEn’s vacated ethanol production facility in Mead, Nebraska.
Please continue checking here for new information.
Winter Web Series
In the first video of our Winter Web Series, NewFields Senior Engineer Bill Butler provides an overview of continued project work at the AltEn site. Significant progress has been made with 58,505 tons of wet cake being safely removed since 2023. While the wet cake solidification and transportation has been paused during the winter months due to colder temperatures, work remains active. The FRG is planning to have 100% of the wet cake removed by the end of 2025. Stay tuned throughout the winter for more updates.
Community Open House
AltEn Site Progress Update
Please join us for an informational meeting about progress at the AltEn site.
The Facility Response Group (FRG) has begun a new phase and our technical representatives will be on hand to share details, respond to questions and have information stations highlighting progress and next steps with the removal of the remaining materials from the site.
We hope to see you there!
Attendees are free to come and go at their convenience during the hours listed to the right. Light refreshments will be available.
DATE
Tuesday, Aug. 22, 2023
SCHEDULE
5 to 6 p.m.
Open House
6 to 6:30 p.m.
Presentation
6:30 to 8 p.m.
Open House continued with information stations
LOCATION
Encounter Life Ministries Church
1540 County Rd 10, Mead, NE 68041
Latest community updates
The responsible, safe remediation of the AltEn site in Mead, Nebraska.
The AltEn Facility Response Group (FRG), as part of Nebraska’s Voluntary Cleanup Program (VCP) and under the direction of the Nebraska Department of Environment and Energy (NDEE), has stabilized the site.
The FRG developed a Remedial Action Plan (RAP) for water stored at the site and is committed to implementing the Water RAP. So far, the FRG has treated over 49 million gallons of process water – 31 million gallons of which has been applied to local farms as a beneficial nutrient source.
The FRG also is developing a RAP for the on-site solids and continues to investigate remediation options for the solid materials at the AltEn site in order to submit the Solids RAP.
As this work continues, the FRG’s top priority is to ensure the continued safety of the surrounding community and environment. NDEE testing has consistently shown no evidence of impacts to water.
This website is a key resource for updates and information about the FRG’s remediation efforts.
Steps the FRG and NDEE have taken to stabilize the site:
-
Developed a Remedial Action Plan for water removal, with nearly [50] million gallons of water treated and applied to land by the end of 2022. An on-site water treatment plant began operating in August 2023.
-
Removed 1,500 tons of trash and debris from the site.
-
Removed more than 5,100 tons of leftover seed from the site’s hoop buildings and silo.
-
Completed the Wet Cake Pilot Project, where more than 12,000 tons of wet cake were solidified and transported to WM’s landfill.
-
Dredged lagoons of solids and water for treatment and land application to solids to be completed in September 2024.
-
Developed a Remedial Action Plan for solids removal with an agreement to continue removing solids through November 2024.
The AltEn Facility Response Group’s top priority is to help ensure the safety of the surrounding community and environment.