AltEn Facility Remediation Response

Updates from the AltEn Facility Response Group (FRG) on remediation efforts at AltEn’s vacated ethanol production facility in Mead, Nebraska.

Please continue checking here for new information.

“Moved Mountains”: Wet Cake Removal Complete; Gov. Pillen Visits Mead to Celebrate Milestone

On Aug. 20, 2025, AltEn Facility Response Group (FRG) completed the solidification and transportation of all wet cake from the AltEn site to WM’s Pheasant Point Landfill.

This follows years of cleanup at the property, which was abandoned by AltEn in 2021. In total, more than 165,000 tons of wet cake were solidified and safely transported since fall of 2023. This summer alone, nearly 85,000 tons of wet cake were taken to the landfill.

On Dec. 9, 2025, Nebraska Gov. Jim Pillen and other elected officials met with Mead community members and project leaders to celebrate the total removal of wet cake from the AltEn facility site. “I don’t think it’s an exaggeration to say we’ve moved mountains,” said Gov. Pillen.

Wet Cake Solidification and Removal Complete

In August of 2025, the AltEn Facility Response Group (FRG) reached a significant milestone of solidifying and removing all of the wet cake from the site abandoned by AltEn. Since 2023, more than 165,000 tons of solidified wet cake have been transferred to WM’s Pheasant Point landfill.

Wet Cake Removal Progress Results
2025

WEEK NO. TRUCKS TONS
4/1 - 4/5 114 2,643
4/7 - 4/12 243 5,624
4/14 - 4/19 252 5,620
4/21 - 4/26 228 5,308
4/28 - 5/3 224 5,182
5/5 - 5/10 277 6,390
5/12 - 5/17 330 7,439
5/19 - 5/24 54 1,158
5/26 - 5/31 221 5,207
6/2 - 6/7 153 3,641
6/9 - 6/14 325 7,114
6/16 - 6/19 206 4,427
6/23 - 6/28 268 5,910
6/30 - 7/5 141 3,282
7/7 - 7/12 99 2,182
7/14 - 7/19 392 9,092
7/21 - 7/26 268 6,468
TOTALS 3,795 86,712

Community Open House

AltEn Site Progress Update

Please join us for an informational meeting about progress at the AltEn site.

The Facility Response Group (FRG) has begun a new phase and our technical representatives will be on hand to share details, respond to questions and have information stations highlighting progress and next steps with the removal of the remaining materials from the site.

 

We hope to see you there!

Attendees are free to come and go at their convenience during the hours listed to the right. Light refreshments will be available.

DATE

Tuesday, Aug. 22, 2023

SCHEDULE

5 to 6 p.m.

Open House

6 to 6:30 p.m.

Presentation

6:30 to 8 p.m.

Open House continued with information stations

LOCATION

Encounter Life Ministries Church
1540 County Rd 10, Mead, NE 68041

Latest community updates

Another Year of Major Progress
Catch up on highlights and actions taken by the Facility Response Group (FRG), under the guidance of the Nebraska Department of Water, Energy and Environment (NDWEE), in 2025 – as well as a look ahead to 2026.
December Community Meeting: 2025 Achievements and Look Ahead to 2026 
On Dec. 9, ERM Newfields Consulting Partner Bill Butler spoke at a community meeting to provide an update about progress at the AltEn site, an overview of the Lagoon Solids Remedial Action Plan (RAP) and other site activities planned...
October Community Update: 2025 Progress
With the arrival of colder weather, the FRG notes progress following the year’s busiest months with updates on former wet cake area grading, Fall land application and the latest groundwater results.

The responsible, safe remediation of the AltEn site in Mead, Nebraska.

The AltEn Facility Response Group (FRG), as part of Nebraska’s Voluntary Cleanup Program (VCP) and under the direction of the Nebraska Department of Water, Energy, and Environment (NDWEE), has stabilized the site.

The FRG developed a Remedial Action Plan (RAP) for water stored at the site and is committed to implementing the Water RAP. The FRG has treated more than 114 million gallons of process water – 50 million gallons of which have been applied to local farms as a beneficial nutrient source.

In August 2025, the FRG completed the solidification and removal of all wet cake from the AltEn site, transporting more than 165,000 tons of material to WM’s Pheasant Point Landfill. In addition, the FRG continues to collaborate with NDWEE to finalize the recommended RAP (Remedial Action Plan) for the remaining on-site solids.

As this work continues, the FRG’s top priority is to ensure the continued safety of the surrounding community and environment. NDWEE testing has consistently shown no evidence of impacts to water.

This website is a key resource for updates and information about the FRG’s remediation efforts.

Steps the FRG and NDWEE have taken to stabilize the site:

The AltEn Facility Response Group’s top priority is to help ensure the safety of the surrounding community and environment.