The below information has been provided in an effort to help keep the community informed on a more frequent basis about progress at the AltEn site.
Ever since AltEn ceased operations at its facility in Mead in 2021, the AltEn Facility Response Group (FRG) has been voluntarily working under the guidance of the Nebraska Department of Environment and Energy (NDEE) to stabilize the AltEn site and develop a Remedial Action Plan (RAP) for the site. The FRG’s top priorities have been and continue to be to help ensure the safety of the surrounding community and environment. To-date, there has been no evidence of impacts to local drinking water.
The FRG is working diligently with the NDEE to identify the most effective and safest methods to address the current environmental conditions on the AltEn site. The remedial action plans (RAP) will recommend remediation for components remaining on-site, including wastewater, sludge, and wet cake.
August 15, 2023
AltEn Community Update
Updates on the solid waste pilot project, water treatment, land application, seed disposal and other site activities.
Solid Waste Pilot Project Update
Site mobilization and pilot project preparation will begin the week of Aug. 21. The pilot will consist of transporting up to 24,000 tons of solidified wet cake between September and November 2023.
Pilot Project Process
Best practices will be followed to solidify and load wet cake for transportation, in addition to managing stormwater, mitigating dust and odor, monitoring air and cleaning both trucks and roads.
Water Treatment Update
The operation of an improved water treatment system has started with positive initial results. Evaluations will continue and if positive results are maintained, more water can be applied to land.
Land Application Update
Land application is planned for Fall 2023 with an estimated 20 million gallons used for land application. The properties on the map below have been identified.
Seed Disposal Update
An estimated 6,675 tons of seed will be transported to a waste-to-energy facility in Tulsa, Okla. Disposal of seed in the South Hoop Building has been completed; disposal in the North Hoop Building is under way. The process is expected to be complete within five months.
Fence Construction
A fence is being constructed around the AltEn site.
Communications
The FRG will hold an open, informational community meeting at Encounter Life Ministries Church on Aug. 22, 2023. This meeting will be held before any wet cake is removed from the site. Please continue checking alteninfo.com for the latest updates.