The below information has been provided in an effort to help keep the community informed on a more frequent basis about progress at the AltEn site.
Ever since AltEn ceased operations at its facility in Mead in 2021, the AltEn Facility Response Group (FRG) has been voluntarily working under the guidance of the Nebraska Department of Environment and Energy (NDEE) to stabilize the AltEn site and develop a Remedial Action Plan (RAP) for the site. The FRG’s top priorities have been and continue to be to help ensure the safety of the surrounding community and environment. To-date, there has been no evidence of impacts to local drinking water.
The FRG is working diligently with the NDEE to identify the most effective and safest methods to address the current environmental conditions on the AltEn site. The remedial action plans (RAP) will recommend remediation for components remaining on-site, including wastewater, sludge, and wet cake.
August 20, 2024
Wet Cake Removal
Northeast Lagoon: Liner Removal
Lagoon Liner Removal and Dredging
The efforts to remove total suspended solids (TSS) from the Southeast Lagoon continues through use of a hydraulic dredge, which reduces potential impact to the site’s water treatment plant (WTP) operations. Geotubes reduce the amount of moisture in the dredged solids. Southeast Lagoon dredging is expected to be completed in September.
A similar liner removal process and solids consolidation is happening in the Northwest Lagoon, with the process anticipated to be completed in September, as well.
Several options for lagoon solids have been evaluated and tested.
Stormwater Best Management Practices
Stormwater best management practice (BMP) improvements along the North Ditch continue. This phase of work is expected to be completed this month.
Lagoon Water Treatment and Land Application
Groundwater Monitoring – June 2024
Other Site Activities
We have made progress with several other on-site activities: Northwest Lagoon subsoil sampling is completed, with results to be shared in September; the new on-site tornado shelter has been installed; new air quality monitors are being set up; groundwater sampling will be done in the coming months.
Stay Informed
Check alteninfo.com for the latest updates about AltEn site activities.