AltEn Facility Remediation Response – Explanatory Posters

AltEn vacated its ethanol production facility in Mead in 2021. Since that time, the AltEn Facility Response Group (FRG) has been voluntarily working, under the direction of the Nebraska Department of Environment and Energy (NDEE), to stabilize the site and develop Remedial Action Plans (RAPs) for the water and the solids remaining on-site. These posters explain the work that has been accomplished to date as well as details specifics of the Solid Waste Pilot Project.
AltEn Solid Waste Pilot Project – Fact Sheet

The FRG is committed to the work we are doing at the AltEn site and is pleased to share our progress of the Solid Waste Pilot Project and steps to be completed from August to November 2023.
AltEn Solid Waste Pilot Program – Fact Sheet

A progress report to update the NDEE on the status of the emergency response measures and interim response at the AltEn site.
AltEn Facility Remediation Response – One Pager

A progress report to update the NDEE on the status of the emergency response measures and interim response at the AltEn site.
AltEn Community Update from the Facility Response Group

Groundwater monitoring, suppression of windblown materials, potential solutions for remaining wet cake and sludge solids, and upcoming spring land application
AltEn Community Update from the Facility Response Group

Groundwater monitoring, solutions for wastewater on the AltEn site, and potential solutions for remaining wet cake and sludge solids.
AltEn Community Update from the Facility Response Group

Groundwater monitoring, submission of the water RAP, and potential solutions for remaining wet cake and sludge solids.
AltEn FRG Water RAP Submission

A progress report to update the NDEE on the status of the emergency response measures and interim response at the AltEn site.
AltEn Community Update from the Facility Response Group

Proposed remedies for wastewater on the site, repairs to the temporary Posi-Shell, and major initiatives underway.
Groundwater Delineation Work Plan

A progress report to update the NDEE on the status of the emergency response measures and interim response at the AltEn site.